What best describes a Prioritized Requirements List (PRL)?

The correct answer is B. High-level prioritized requirements list. A Prioritized Requirements List (PRL) is exactly what its name describes - a high-level, ranked list of the requirements for a project or product, making B correct by definition. Option A describes a Ways of Working (WoW) document or team agreement, not a PRL. Option C…

DSDM Framework

Question

What best describes a Prioritized Requirements List (PRL)?

Options

  • AHigh-level definition of the tools, techniques and customs
  • BHigh-level prioritized requirements list
  • CHigh-level definition of the over-arching business driver
  • DHigh-level schedule of Project Increments

How the community answered

(25 responses)
  • B
    96% (24)
  • D
    4% (1)

Explanation

A Prioritized Requirements List (PRL) is exactly what its name describes - a high-level, ranked list of the requirements for a project or product, making B correct by definition. Option A describes a Ways of Working (WoW) document or team agreement, not a PRL. Option C describes a Vision Statement, which captures the overarching business driver or purpose. Option D describes a Program Board or PI Planning schedule, which maps work across Project Increments in SAFe or similar frameworks.

Memory tip: Let the acronym guide you - PRL = Prioritized Requirements List. Every word in the name IS the definition. If an exam choice restates the acronym's meaning, that's your answer.