AD0-E907 · Question #75
A client wants to integrate Workfront Boards to track campaign deliverables. Which configuration is recommended?
The correct answer is B. Set up custom columns based on deliverable status. Setting up custom columns based on deliverable status (B) is the recommended approach because Workfront Boards are designed to reflect your team's actual workflow - custom columns let you map each stage of a campaign deliverable (e.g., "Brief," "In Review," "Approved") so the…
Question
A client wants to integrate Workfront Boards to track campaign deliverables. Which configuration is recommended?
Options
- AAssign system administrator rights to the team lead
- BSet up custom columns based on deliverable status
- CEnable proofing for all team members
- DUse default Board settings without modification
How the community answered
(40 responses)- A13% (5)
- B78% (31)
- C3% (1)
- D8% (3)
Explanation
Setting up custom columns based on deliverable status (B) is the recommended approach because Workfront Boards are designed to reflect your team's actual workflow - custom columns let you map each stage of a campaign deliverable (e.g., "Brief," "In Review," "Approved") so the board mirrors real-world progress rather than a generic structure.
Why the distractors are wrong:
- A is a permissions/security decision unrelated to board configuration - giving admin rights to a team lead doesn't help organize deliverables.
- C (enabling proofing) is a separate Workfront feature for document review and approval; it doesn't configure how the board tracks work.
- D ignores the core value of Boards - default settings are too generic to reflect campaign-specific deliverable stages.
Memory tip: Think "custom columns = custom campaign." Boards are only as useful as they are specific to your workflow - the exam will favor answers that tailor the tool to the use case over generic or unrelated configurations.
Topics
Community Discussion
No community discussion yet for this question.