AD0-E907 · Question #106

How can a project manager ensure high-priority projects receive adequate resources?

The correct answer is B. By using portfolio prioritization. Portfolio prioritization (B) is the correct approach because it allows organizations to rank and allocate resources across competing projects based on strategic value - ensuring high-priority initiatives receive funding, personnel, and tools before lower-priority ones. Why the…

Workfront Object Model

Question

How can a project manager ensure high-priority projects receive adequate resources?

Options

  • ABy setting task constraints
  • BBy using portfolio prioritization
  • CBy increasing task durations
  • DBy enabling auto-provisioning for resources

How the community answered

(69 responses)
  • A
    13% (9)
  • B
    78% (54)
  • C
    3% (2)
  • D
    6% (4)

Explanation

Portfolio prioritization (B) is the correct approach because it allows organizations to rank and allocate resources across competing projects based on strategic value - ensuring high-priority initiatives receive funding, personnel, and tools before lower-priority ones.

Why the distractors are wrong:

  • A (Task constraints) - These control when or how a task runs (e.g., must-start-on dates), not how resources are distributed across projects.
  • C (Increasing task durations) - Stretching timelines doesn't direct more resources to priority work; it often signals poor planning or resource scarcity.
  • D (Auto-provisioning) - This is an IT/cloud concept for automatically scaling infrastructure, not a project management resource allocation strategy.

Memory tip: Think of a portfolio as a stock portfolio - just as an investor puts more money into high-yield stocks, a portfolio manager puts more resources into high-value projects. "Portfolio = prioritized investment."

Topics

#portfolio prioritization#resource management#project priority