AD0-E907 · Question #27

Which elements can be configured to customize task dependencies in project initiation? (Select two.)

The correct answer is B. Task predecessors C. Task constraints. Task predecessors (B) and task constraints (C) are the two elements directly used to customize task dependencies during project initiation. Predecessors define the sequential relationship between tasks (e.g., Task B cannot start until Task A finishes), while constraints set…

Workfront Object Model

Question

Which elements can be configured to customize task dependencies in project initiation? (Select two.)

Options

  • ARole-based assignments
  • BTask predecessors
  • CTask constraints
  • DGroup-level sharing permissions

How the community answered

(36 responses)
  • A
    17% (6)
  • B
    75% (27)
  • D
    8% (3)

Explanation

Task predecessors (B) and task constraints (C) are the two elements directly used to customize task dependencies during project initiation. Predecessors define the sequential relationship between tasks (e.g., Task B cannot start until Task A finishes), while constraints set time-based rules (e.g., a task must start no earlier than a specific date) - both directly shape how tasks depend on and relate to each other in the project schedule.

Why the distractors are wrong:

  • A (Role-based assignments) controls who does a task, not when or in what order tasks happen - it's about resource allocation, not dependency logic.
  • D (Group-level sharing permissions) governs who can see or edit the project, which is an access control setting, not a scheduling or dependency configuration.

Memory tip: Think "dependencies = sequence + timing" - predecessors handle sequence (what comes before), constraints handle timing (when it can happen). Assignments and permissions answer "who," not "when."

Topics

#task dependencies#task predecessors#task constraints#project initiation