AD0-E907 · Question #74
A team lead wants to monitor deliverables for a multi-phase project. They need to ensure tasks are completed in order and on time. What Workfront feature should they use?
The correct answer is A. Sequential task dependencies in Gantt charts. Sequential task dependencies in Gantt charts (A) are the right tool because they let a team lead define which tasks must finish before others can begin, visually map the project timeline across phases, and track whether each deliverable is completed on schedule. Audit trail…
Question
A team lead wants to monitor deliverables for a multi-phase project. They need to ensure tasks are completed in order and on time. What Workfront feature should they use?
Options
- ASequential task dependencies in Gantt charts
- BAudit trail reports
- CFinancial tracking dashboard
- DTime log entries
How the community answered
(27 responses)- A74% (20)
- B4% (1)
- C15% (4)
- D7% (2)
Explanation
Sequential task dependencies in Gantt charts (A) are the right tool because they let a team lead define which tasks must finish before others can begin, visually map the project timeline across phases, and track whether each deliverable is completed on schedule. Audit trail reports (B) record who changed what in the system - useful for compliance, not for managing task order or deadlines. A financial tracking dashboard (C) monitors budgets and costs, not task sequencing or completion timelines. Time log entries (D) capture how long individuals spend on work, but don't enforce or visualize task order across phases.
Memory tip: Think "sequential = sequence = order." Gantt charts are the classic project management tool for visualizing task order and dependencies over time - if the question mentions order and phases, Gantt with sequential dependencies is almost always the answer.