Cisco
840-450 · Question #69
840-450 Question #69: Real Exam Question with Answer & Explanation
The correct answer is D. a factor that acts as the catalyst for growth in the areas that are most important to the business. See the full explanation below for the reasoning.
Question
What is the definition of a business priority?
Options
- Aa measurable result of an activity or process within the business
- Ban important business initiative that enables the business to transition to the target state
- Cthe result of an analysis of political, economic, social, technology, legal, or environmental factors
- Da factor that acts as the catalyst for growth in the areas that are most important to the business
Community Discussion
No community discussion yet for this question.