nerdexam
Microsoft

74-344 · Question #82

You work for an organization that uses Project Server 2013. Single-entry mode is disabled. Team members enter updates in Project Web App (PWA) through the Tasks page. You need to select a tracking…

The correct answer is B. Actual work done and work remaining. See the full explanation below for the reasoning.

Question

You work for an organization that uses Project Server 2013. Single-entry mode is disabled. Team members enter updates in Project Web App (PWA) through the Tasks page. You need to select a tracking method that enables the following scenario:

  • During week one, a team member enters a total of 20 hours of actual

work.

  • During week two, the team member modifies the total to 30 hours of

actual work.

  • Following a save, the work value remains the same, and the remaining

work value decreases.

  • Additionally, the percent of work complete increases.

Which tracking method should you use?

Options

  • APercent of work complete
  • BActual work done and work remaining
  • CHours of work done per period
  • DReport hours worked every day

How the community answered

(37 responses)
  • A
    14% (5)
  • B
    76% (28)
  • C
    3% (1)
  • D
    8% (3)

Community Discussion

No community discussion yet for this question.

Full 74-344 Practice