The correct answer is A. Delegate yourself as the resource and update their timesheet as them.. See the full explanation below for the reasoning.
Question
You are a resource manager for an organization that uses Project Server 2013 in Project Server Permission Mode with default security settings. One of the resources you manage is unexpectedly out of the office, and timesheets are due today. The resource has told you their current work and what should be on their timesheet. You do not have access to the resource's corporate user ID and password. You need to meet the submission deadline by updating their timesheet so that the system recognizes you as your resource. What should you do?
Options
- ADelegate yourself as the resource and update their timesheet as them.
- BReassign the tasks to your user ID and update the tasks as the resource.
- CWait until the resource can sign onto the system and do it themselves.
- DAsk the administrator to give you the Update Tasks for the resource's permission.