You are a project manager in an organization that uses Project Server 2013. You manage a project that has Baseline0 set. There are enterprise custom fields with formulas that make calculations by…
The correct answer is B. Open your project in Project Professional 2013 and copy Baseline0 into Baseline1. See the full explanation below for the reasoning.
Question
You are a project manager in an organization that uses Project Server 2013. You manage a project that has Baseline0 set. There are enterprise custom fields with formulas that make calculations by using the Baseline0 fields. You are planning a major rescheduling in your project and intend to update the project baseline so the formulas in the enterprise custom fields take the new values of the baseline fields. However, for future reference, you want to keep your original baseline. You need to update the project baseline without losing the original values. What should you do?
Options
- AOpen you project in Project Professional 2013.
- BOpen your project in Project Professional 2013 and copy Baseline0 into Baseline1.
- COpen your project in Project Professional 2013 and set a new Baseline0.
- DOpen your project in Project Professional 2013, set a new Baseline1, and save and publish
How the community answered
(48 responses)- A8% (4)
- B77% (37)
- C2% (1)
- D13% (6)