You are an area project manager who uses Project Server 2013. You are aligning and planning your team's availability against existing and proposed projects. You need to estimate your team members'…

The correct answer is A. Create a resource plan for the planned project, assign team members, and estimate the. See the full explanation below for the reasoning.

Question

You are an area project manager who uses Project Server 2013. You are aligning and planning your team's availability against existing and proposed projects. You need to estimate your team members' work load for future time periods against projects that have not completed a work breakdown structure (WBS) yet. You need to account for both existing and planned projects. What should you do?

Options

  • ACreate a resource plan for the planned project, assign team members, and estimate the
  • BCreate generic resources in the Resource Center and add them to the project in the Project
  • CUse budget work resources and assign them to tasks in the project file to view resource load.
  • DExport the project tasks to Microsoft Excel, add your proposed projects, and plan your future

How the community answered

(31 responses)
  • A
    77% (24)
  • B
    3% (1)
  • C
    6% (2)
  • D
    13% (4)