You are a project manager who uses Project Server 2013 and Project Professional 2013. You build your project plan. In the least amount of time, you need to assign resources to your plan based on…

The correct answer is C. Open your project in Project Professional 2013 and use the Build Team From Enterprise. See the full explanation below for the reasoning.

Question

You are a project manager who uses Project Server 2013 and Project Professional 2013. You build your project plan. In the least amount of time, you need to assign resources to your plan based on their availability. What should you do?

Options

  • AOpen your project in the Project Web App (PWA) and use the Resource Center Availability
  • BOpen your project in Project Professional 2013 and add resources to your plan.
  • COpen your project in Project Professional 2013 and use the Build Team From Enterprise
  • DOpen your project in the Project Web App (PWA) and use the Resource Center

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    5% (2)
  • C
    82% (31)
  • D
    11% (4)