Question

You are a program manager for an organization that uses Project Server 2013. You are responsible for implementing a data warehouse that compiles relational data from many business areas. Your project managers need to be able to manage the implementation for a business area as separate projects, while still recognizing the dependencies at a program level. You need to maintain ownership and authority of key program dates at the program level. What should you do?

Options

  • ACreate one project file for all project managers that includes the program-level tasks and
  • BCreate and publish a master project file with general durations for each business area
  • CHave the project managers create, save, and publish sub-projects for each area.
  • DCreate a master project and insert your projects, but never publish the file on the server.