You are a program manager for an organization that uses Project Server 2013. You are responsible for implementing a data warehouse that compiles relational data from many business areas. Your…
The correct answer is C. Have the project managers create, save, and publish sub-projects for each area. See the full explanation below for the reasoning.
Question
You are a program manager for an organization that uses Project Server 2013. You are responsible for implementing a data warehouse that compiles relational data from many business areas. Your project managers need to be able to manage the implementation for a business area as separate projects, while still recognizing the dependencies at a program level. You need to maintain ownership and authority of key program dates at the program level. What should you do?
Options
- ACreate one project file for all project managers that includes the program-level tasks and
- BCreate and publish a master project file with general durations for each business area
- CHave the project managers create, save, and publish sub-projects for each area.
- DCreate a master project and insert your projects, but never publish the file on the server.
How the community answered
(20 responses)- A5% (1)
- B5% (1)
- C75% (15)
- D15% (3)
Community Discussion