You are a program manager for a company that uses Project Server 2013 and Project Professional 2013. You manage the implementation of a data warehouse. You have set up your program master project…

The correct answer is B. Open the program-level project from Project Web App (PWA) by using Project Professional D. Open each of the required subprojects from the Project Web App (PWA) by using Project. See the full explanation below for the reasoning.

Question

You are a program manager for a company that uses Project Server 2013 and Project Professional 2013. You manage the implementation of a data warehouse. You have set up your program master project with subprojects for each implementation area. You need to make edits to the dependencies between projects. What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)

Options

  • AView the subproject in Project Web App (PWA) and choose Edit.
  • BOpen the program-level project from Project Web App (PWA) by using Project Professional
  • COpen the program-level project and the subproject from the Project Web App (PWA) and
  • DOpen each of the required subprojects from the Project Web App (PWA) by using Project
  • EView the program-level project in Project Web App (PWA) and choose Edit.

How the community answered

(60 responses)
  • A
    8% (5)
  • B
    83% (50)
  • C
    5% (3)
  • E
    3% (2)