You are a project manager in an organization that uses Project Online. Project managers have access to Project Professional 2013 for schedule management. You create a project schedule with resource…

The correct answer is A. Use Task Inspector to reschedule the tasks. See the full explanation below for the reasoning.

Question

You are a project manager in an organization that uses Project Online. Project managers have access to Project Professional 2013 for schedule management. You create a project schedule with resource assignments on Monday. No resources are overallocated. However, on Tuesday, you open the same project schedule and discover on several of your tasks that resources show as overallocated. Your project has a lower priority than other projects in the organization. You need to solve the overallocation by adjusting the Scheduled Start for the resources on your tasks to when the resources are available. What should you do?

Options

  • AUse Task Inspector to reschedule the tasks.
  • BUse the Resource Usage view to go to next overallocation.
  • CUse Team Planner view to reassign the tasks.
  • DUse Task Information to change the priority number of the tasks.

How the community answered

(26 responses)
  • A
    81% (21)
  • B
    4% (1)
  • C
    12% (3)
  • D
    4% (1)