74-344 · Question #66
An organization is performing a Portfolio Analysis with Project Server 2013 to determine the projects that will be executed the next year. The company has the following base staff: one application…
The correct answer is C. Enter new start dates. See the full explanation below for the reasoning.
Question
An organization is performing a Portfolio Analysis with Project Server 2013 to determine the projects that will be executed the next year. The company has the following base staff: one application developer, one business analyst, one project administrator, and one trainer. The Resource Analysis is shown the following exhibit. (Click the Exhibit button.) You need to include all projects and resolve the overallocations in the most cost-effective way. What should you do?
Exhibit
Options
- AHire an additional business analyst.
- BRevise the primary cost constraint.
- CEnter new start dates.
- DUse the Force In/Out feature.
How the community answered
(23 responses)- A4% (1)
- B13% (3)
- C78% (18)
- D4% (1)