nerdexam
Microsoft

74-344 · Question #67

Your company uses Project Server 2013 to evaluate and select projects based on a primary cost constraint, as well as a secondary constraint of internal rate of return (IRR). Management authorizes a…

The correct answer is B. Create the analysis and, during the cost analysis, introduce the secondary constraint to. See the full explanation below for the reasoning.

Question

Your company uses Project Server 2013 to evaluate and select projects based on a primary cost constraint, as well as a secondary constraint of internal rate of return (IRR). Management authorizes a budget and establishes a minimal IRR of 5% to execute any project the following year. Your company has never analyzed constraints other than cost. As the portfolio analysis expert, you need to recommend a reasonable approach to perform the analysis. What should you recommend?

Options

  • ACreate a new analysis through portfolio analysis and select the primary and secondary
  • BCreate the analysis and, during the cost analysis, introduce the secondary constraint to
  • CCreate a new analysis through Portfolio Analysis and select the primary cost constraint.
  • DCreate the analysis and, during the cost analysis, introduce the secondary constraint to

How the community answered

(46 responses)
  • A
    7% (3)
  • B
    76% (35)
  • C
    15% (7)
  • D
    2% (1)

Community Discussion

No community discussion yet for this question.

Full 74-344 Practice