74-344 · Question #68

You are a program manager in an organization that uses Project Server 2013. The allow master projects to be saved and published function is not enabled. Your program contains seven active projects…

The correct answer is B. Select all seven projects, open in a temporary master project, expand all tasks, and filter for. See the full explanation below for the reasoning.

Question

You are a program manager in an organization that uses Project Server 2013. The allow master projects to be saved and published function is not enabled. Your program contains seven active projects managed in Project Online. You need a way to review the tasks flagged as milestones in all seven active projects at one time. You open Project Center in Project Web App (PWA). What should you do next?

Options

  • ASelect all seven projects and choose Export to Excel on the ribbon.
  • BSelect all seven projects, open in a temporary master project, expand all tasks, and filter for
  • CSelect the Subprojects check box on the ribbon.
  • DCreate a custom filter in which the Milestone field equals Yes, and apply it to the view.

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    84% (26)
  • C
    10% (3)
  • D
    3% (1)