74-344 · Question #69

74-344 Question #69: Real Exam Question with Answer & Explanation

The correct answer is C. Access the Project Details pages, verify that the sections are completed, and click Submit.. See the full explanation below for the reasoning.

Question

You work for a multinational corporation which uses Project Server 2013 to plan and control the projects in different business units. Each business unit has its own portfolio of projects but can participate in strategic projects. The Project Management Office (PMO) configures as many Enterprise Project Types as necessary to create new products, launch marketing campaigns, and deploy new lines of business tools to comply with the governance processes. A business unit creates a new proposal, and your team waits for the new proposal approval, which will provide the information necessary to begin this proposal. In the Project Center, the stakeholders are able to view the phases and stages of each proposal, and your proposal has not moved since the last time you saved it in Project Web App (PWA). The sponsor waits for the notification to review and authorize the next stage of the project. You need to ensure the project moves through its lifecycle. What should you do first?

Options

  • AAccess the Project Details pages, click Options, and select Restart the Workflow.
  • BAccess the Project Details pages and publish the schedule.
  • CAccess the Project Details pages, verify that the sections are completed, and click Submit.
  • DAccess the Project Center, select the project, and change the Project Type.