74-344 · Question #64
You are a project manager who uses Project Server 2013. You have an in-progress project. A resource who has reported actual work on the project is no longer available. You want to preserve their…
The correct answer is C. Open the project in Project Professional 2013. See the full explanation below for the reasoning.
Question
You are a project manager who uses Project Server 2013. You have an in-progress project. A resource who has reported actual work on the project is no longer available. You want to preserve their actual work. You need to replace this resource with a newly-hired resource. What should you do?
Options
- AOpen the project in Project Professional 2013.
- BOpen the project in Project Web App (PWA) and manually edit the resource in the Gantt
- COpen the project in Project Professional 2013.
- DOpen the project in Project Professional 2013 and manually edit the resource in the Gantt
How the community answered
(37 responses)- A5% (2)
- B3% (1)
- C78% (29)
- D14% (5)
Community Discussion
No community discussion yet for this question.