nerdexam
Microsoft

74-344 · Question #63

You are a project manager for an organization that uses Project Server 2013. You have the appropriate permissions to set all baselines. Your project experiences a scope change, which requires you to…

The correct answer is B. Use an unused baseline to set a new baseline. See the full explanation below for the reasoning.

Question

You are a project manager for an organization that uses Project Server 2013. You have the appropriate permissions to set all baselines. Your project experiences a scope change, which requires you to add tasks to the end of the schedule. You need to retain historical information for both completed and in-progress tasks but create a baseline that includes the newly-selected tasks. You check out your schedule in Project Web App (PWA) for editing and select the newly-added tasks. What should you do next?

Options

  • ASet an interim plan.
  • BUse an unused baseline to set a new baseline.
  • CClear the baseline and then set a baseline for the entire project.
  • DSet a baseline for only the selected tasks.

How the community answered

(20 responses)
  • A
    10% (2)
  • B
    70% (14)
  • C
    5% (1)
  • D
    15% (3)

Community Discussion

No community discussion yet for this question.

Full 74-344 Practice