You are a project manager for an organization that uses Project Server 2013. You have the appropriate permissions to set all baselines. Your project experiences a scope change, which requires you to…
The correct answer is B. Use an unused baseline to set a new baseline. See the full explanation below for the reasoning.
Question
You are a project manager for an organization that uses Project Server 2013. You have the appropriate permissions to set all baselines. Your project experiences a scope change, which requires you to add tasks to the end of the schedule. You need to retain historical information for both completed and in-progress tasks but create a baseline that includes the newly-selected tasks. You check out your schedule in Project Web App (PWA) for editing and select the newly-added tasks. What should you do next?
Options
- ASet an interim plan.
- BUse an unused baseline to set a new baseline.
- CClear the baseline and then set a baseline for the entire project.
- DSet a baseline for only the selected tasks.
How the community answered
(20 responses)- A10% (2)
- B70% (14)
- C5% (1)
- D15% (3)