You are a project manager in an organization that has recently installed Project Server 2013. The organization is new to project management and to Project Server 2013. The organization has…
The correct answer is A. Resources should go to the Tasks page of their Newsfeed. D. Resources should select the check box next to each task. See the full explanation below for the reasoning.
Question
You are a project manager in an organization that has recently installed Project Server 2013. The organization is new to project management and to Project Server 2013. The organization has experience with Microsoft SharePoint task lists. The free form tracking method has been selected in Project Server 2013. You plan to create task assignments. You need to implement update procedures that meet the following requirements:
- Resources need to be able to report on a task when it is completed.
- Resources should NOT have the ability to report on partially
completed tasks.
- Resources should be able to easily and quickly update project tasks.
Which two update procedures should you implement? (Each correct answer presents part of the solution. Choose two.)
Options
- AResources should go to the Tasks page of their Newsfeed.
- BResources should go to the Tasks page of Project Web App (PWA).
- CResources should enter hours in the work column.
- DResources should select the check box next to each task.
How the community answered
(33 responses)- A76% (25)
- B9% (3)
- C15% (5)
Community Discussion