You are a project manager for an organization that uses Project Server 2013. You and other project managers use Project Professional 2013 to manage projects. The resources on your project are…

The correct answer is A. Select all tasks that are partially complete or did not start as scheduled and move incomplete. See the full explanation below for the reasoning.

Question

You are a project manager for an organization that uses Project Server 2013. You and other project managers use Project Professional 2013 to manage projects. The resources on your project are overallocated due to work assigned across the enterprise. As a result, some work on your project does not finish as scheduled. Some tasks are left partially complete. Other tasks did not start at all. You need to resolve this issue. What should you do?

Options

  • ASelect all tasks that are partially complete or did not start as scheduled and move incomplete
  • BMove all tasks that are partially complete back one week.
  • CMove only the tasks that did not start forward by one week.
  • DSelect all tasks that are partially complete or did not start as scheduled, and move completed

How the community answered