74-344 · Question #78
You work for an organization that uses Project Server 2013. You are updating your assigned task information from your Microsoft SharePoint task list. You need to ensure that the appropriate fields…
The correct answer is A. Task Status C. Predecessors D. Work. Task Status Choose the descriptor that most accurately reflects the status of the set of tasks that fall within this summary task. If you are just planning a project and none of the tasks in this summary task have begun, choose Not Started.
Question
You work for an organization that uses Project Server 2013. You are updating your assigned task information from your Microsoft SharePoint task list. You need to ensure that the appropriate fields are updated. Which three standard fields can be updated when in SharePoint? (Each correct answer presents a complete solution. Choose three.)
Options
- ATask Status
- B% complete
- CPredecessors
- DWork
- EDuration
How the community answered
(36 responses)- A81% (29)
- B6% (2)
- E14% (5)
Explanation
Task Status Choose the descriptor that most accurately reflects the status of the set of tasks that fall within this summary task. If you are just planning a project and none of the tasks in this summary task have begun, choose Not Started.
Topics
Community Discussion
No community discussion yet for this question.