74-344 · Question #23

You are a project manager for an organization that uses Project Server 2013. As part of a regular project review, you notice that several tasks of one of your projects that should be finished are…

The correct answer is A. Open the project for editing in Project Web App (PWA). D. Type today's date in the field Update work as complete through. E. click the Update Project button. A: You can track the time that you have spent working on tasks, projects, and non-project activities by using timesheets in Project Web App (PWA). D: Mark as complete.

Troubleshoot Client Issues

Question

You are a project manager for an organization that uses Project Server 2013. As part of a regular project review, you notice that several tasks of one of your projects that should be finished are outdated. You need to update those tasks with the exact percent complete as of today. Which three steps should you perform? (Each correct answer presents part of the solution. Choose three.)

Options

  • AOpen the project for editing in Project Web App (PWA).
  • BType today's date in the Actual Start field for each outdated task.
  • COpen the project for editing in Project Professional 2013.
  • DType today's date in the field Update work as complete through.
  • Eclick the Update Project button.

How the community answered

(50 responses)
  • A
    84% (42)
  • B
    10% (5)
  • C
    6% (3)

Explanation

A: You can track the time that you have spent working on tasks, projects, and non-project activities by using timesheets in Project Web App (PWA). D: Mark as complete.

Topics

#task completion#percent complete#Update Project#Project Web App