74-344 · Question #22

You are a project manager in an organization that uses Project Server 2013. Project team members submit updates to tasks through Project Web App (PWA). A project team member clicks Remove Task, and…

The correct answer is D. Assign the team member to the task and publish the project. See the full explanation below for the reasoning.

Question

You are a project manager in an organization that uses Project Server 2013. Project team members submit updates to tasks through Project Web App (PWA). A project team member clicks Remove Task, and you approve it. You apply this change to the project. The team member indicates that they only want to hide the task from that particular view, not remove the task permanently. You need to ensure the task is returned to the Tasks page so it can be properly hidden. What should you do?

Options

  • AMark the task as active and publish the project.
  • BTell the team member to choose Add Row and click Add Team Task.
  • CTell the team member to modify the filter to show incomplete tasks.
  • DAssign the team member to the task and publish the project.

How the community answered

(18 responses)
  • B
    6% (1)
  • C
    11% (2)
  • D
    83% (15)