Microsoft
74-344 · Question #21
Your organization uses Project Server 2013. For security reasons, only individuals inside your organization have access to Project Web App (PWA). You want to keep track of progress made by a…
The correct answer is C. Assign the resource manager as the Assignment Owner. See the full explanation below for the reasoning.
Question
Your organization uses Project Server 2013. For security reasons, only individuals inside your organization have access to Project Web App (PWA). You want to keep track of progress made by a third-party vendor. The vendor will email task progress to the resource manager. The resource manager will be responsible for reporting vendor progress back to the project manager in PWA. You need to enable this functionality. You add the vendor as a resource in Project Server. What should you do next?
Options
- AAssign the resource manager as the Status Manager.
- BAssign the project manager as the Assignment Owner.
- CAssign the resource manager as the Assignment Owner.
- DAssign the administrator as the Status Manager.
How the community answered
(27 responses)- A4% (1)
- B11% (3)
- C70% (19)
- D15% (4)
Community Discussion
No community discussion yet for this question.