Your organization uses Project Server 2013. You are the project manager of a schedule. Team Members send you emails with their percentage complete on their assignments. Your organization only uses…

The correct answer is B. In PWA, open Project Center. C. In PWA, open Project Center. See the full explanation below for the reasoning.

Question

Your organization uses Project Server 2013. You are the project manager of a schedule. Team Members send you emails with their percentage complete on their assignments. Your organization only uses the following two percentages for tracking tasks:

  • 50% for tasks that are started
  • 100% for tasks that are completed

You have Project Web App (PWA) and use the information from the emails to update the tasks. You need to update the tasks in PWA. What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)

Options

  • AIn PWA, open the Tasks screen, select the task(s), and enter 50% or 100% in the %
  • BIn PWA, open Project Center.
  • CIn PWA, open Project Center.
  • DIn PWA, open the Microsoft SharePoint site for the schedule, select the task(s), and update

How the community answered

(34 responses)
  • A
    9% (3)
  • B
    71% (24)
  • D
    21% (7)