Microsoft
74-344 · Question #24
74-344 Question #24: Real Exam Question with Answer & Explanation
Sign in or unlock 74-344 to reveal the answer and full explanation for question #24. The question stem and answer options stay visible for context.
Question
Your organization uses Project Server 2013. You are the project manager of a schedule. Team Members send you emails with their percentage complete on their assignments. Your organization only uses the following two percentages for tracking tasks: - 50% for tasks that are started - 100% for tasks that are completed You have Project Web App (PWA) and use the information from the emails to update the tasks. You need to update the tasks in PWA. What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)
Options
- AIn PWA, open the Tasks screen, select the task(s), and enter 50% or 100% in the %
- BIn PWA, open Project Center.
- CIn PWA, open Project Center.
- DIn PWA, open the Microsoft SharePoint site for the schedule, select the task(s), and update
Unlock 74-344 to see the answer
You've previewed enough free 74-344 questions. Unlock 74-344 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.