74-344 · Question #25
As a team member, you submit your timesheet for approval in Project Server 2013. After sending the timesheet to the timesheet manager, you realize you forgot to include some work. You need to ensure…
The correct answer is C. Recall the timesheet from the Manage Timesheets page. Make your changes and re-send it. D. Ask your timesheet manager to reject your timesheet. Make your changes and re-send it. See the full explanation below for the reasoning.
Question
As a team member, you submit your timesheet for approval in Project Server 2013. After sending the timesheet to the timesheet manager, you realize you forgot to include some work. You need to ensure that the work is added to your timesheet. What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)
Options
- AMake an adjusting entry on your next timesheet and then submit that one.
- BRe-open it immediately. Make your changes and re-send it.
- CRecall the timesheet from the Manage Timesheets page. Make your changes and re-send it.
- DAsk your timesheet manager to reject your timesheet. Make your changes and re-send it.
How the community answered
(34 responses)- A3% (1)
- B12% (4)
- C85% (29)