74-344 · Question #59
You work in an organization that uses Project Online. Project managers have full control over resource assignments. You work in the Project Management Office (PMO) and discover that two of your…
The correct answer is B. Manage Project assignments. C. Manage Microsoft SharePoint task assignments. See the full explanation below for the reasoning.
Question
You work in an organization that uses Project Online. Project managers have full control over resource assignments. You work in the Project Management Office (PMO) and discover that two of your critical resources are overallocated in the Resource Center for future work. They are critical resources because they have specialized skills that no one else in your organization has, and they are integral to several projects. You need to determine how to correct the overallocation of these resources. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
Options
- AManage resource plan task assignments.
- BManage Project assignments.
- CManage Microsoft SharePoint task assignments.
- DManage Project issue assignments.
How the community answered
(49 responses)- A14% (7)
- B76% (37)
- D10% (5)
Community Discussion
No community discussion yet for this question.