Question

You are a resource manager and manage a project with Project Server 2013 and Project Professional 2013. Without notice, one of your key resources decides to take a leave of absence for 30 days. You need to account for the absent resource and assess how the absence will affect your schedule. What should you do?

Options

  • AOpen Project Professional 2013 and manually reschedule the tasks associated with
  • BOpen the resource from the Resource Center view and edit the resource in Project
  • COpen the Project Web App (PWA), go to the Resource Center, and change the earliest
  • DOpen your project file in Project Professional 2013 and adjust the units for your resource to