74-344 · Question #58

You are a project administrator and are implementing Project Server 2013 for a large organization. You are asked to ensure that resource assignments, work load, and completion of work can be…

The correct answer is A. Define your information hierarchy in the server settings by using the Resource Breakdown. See the full explanation below for the reasoning.

Question

You are a project administrator and are implementing Project Server 2013 for a large organization. You are asked to ensure that resource assignments, work load, and completion of work can be reported and rolled up by organizational structure. You need employ the correct functionality in order to configure Project Server 2013. What should you do?

Options

  • ADefine your information hierarchy in the server settings by using the Resource Breakdown
  • BUse the Resource Center in Project Web App (PWA) to edit your resources and use the
  • CDefine your information hierarchy in the server settings by using the Project Department field,
  • DRequire all project managers to use Project Professional 2013 to assign a department to the

How the community answered

(41 responses)
  • A
    73% (30)
  • B
    7% (3)
  • C
    17% (7)
  • D
    2% (1)