Question

You are a project manager for an organization that uses Project Server 2013. You are evaluating resource information in the Resource Center. The following information is presented to you on the Resource Availability page: You need to determine if a team member has available capacity to assist on another project or if this team member is overallocated. What should you do?

Options

  • AThe team member has 32 hours available for enterprise projects and should be assigned to
  • BThe team member has 8 hours available for enterprise projects and should be assigned to
  • CThe team member is overallocated by 32 hours on enterprise projects and is not available to
  • DThe team member is overallocated by 8 hours on enterprise projects and is not available to