nerdexam
Microsoft

74-344 · Question #54

You are a project manager who uses Project Server 2013 and Project Professional 2013. You build a project with common tasks for which many resources on your team can be used. Because your resources…

The correct answer is D. Create a Generic Work resource and assign it to the same team as the other resources. See the full explanation below for the reasoning.

Question

You are a project manager who uses Project Server 2013 and Project Professional 2013. You build a project with common tasks for which many resources on your team can be used. Because your resources have responsibilities outside of the project, you would like to have them assign themselves to tasks they are able to complete. You need to configure your resources to enable this method of assigning tasks. What should you do?

Options

  • AOpen the Build Team From Enterprise dialog box for the project and change each resource
  • BCreate your project in Project Professional 2013 and publish the file without any resources
  • CCreate your project in Project Professional 2013 and then email it to each resource, asking
  • DCreate a Generic Work resource and assign it to the same team as the other resources.

How the community answered

(59 responses)
  • A
    8% (5)
  • B
    3% (2)
  • C
    15% (9)
  • D
    73% (43)

Community Discussion

No community discussion yet for this question.

Full 74-344 Practice