You are a Project Server 2013 administrator, and you support the Project Management Office (PMO) project managers who need to estimate project hours and costs without knowing the specific resource…

The correct answer is D. Create a generic work resource in the resource center and have project managers use the. See the full explanation below for the reasoning.

Question

You are a Project Server 2013 administrator, and you support the Project Management Office (PMO) project managers who need to estimate project hours and costs without knowing the specific resource names. There are options available to accommodate this request when creating resources on Project Server 2013. You need to allow project managers to plan workload and cost from the task level up. What should you do?

Options

  • ACreate a budget work resource in the resource center and have project managers use the
  • BCreate two custom task level fields named Resource Hours and Resources Costs, and add
  • CHave project managers add resources from the Build Team From Enterprise function when
  • DCreate a generic work resource in the resource center and have project managers use the

How the community answered

(28 responses)
  • A
    7% (2)
  • B
    18% (5)
  • C
    4% (1)
  • D
    71% (20)