A consultant needs to evaluate project management methodologies for a new service deployment on the existing network of a customer. The customer wants to be involved in the end-to-end project…

The correct answer is C. Agile. Agile methodology is designed for iterative delivery with continuous customer involvement and the ability to adapt requirements throughout the project.

Gathering and Clarifying Requirements

Question

A consultant needs to evaluate project management methodologies for a new service deployment on the existing network of a customer. The customer wants to be involved in the end-to-end project progress and be provided with frequent updates. The customer also wants the ability to change the requirements if needed, as the project progresses. Which project management methodology should be used?

Options

  • Athree principles
  • Bphased
  • CAgile
  • DWaterfall

How the community answered

(19 responses)
  • B
    5% (1)
  • C
    89% (17)
  • D
    5% (1)

Why each option

Agile methodology is designed for iterative delivery with continuous customer involvement and the ability to adapt requirements throughout the project.

Athree principles

Three principles is not a recognized standard project management methodology applicable to IT service deployments.

Bphased

Phased methodology uses sequential, gated phases that limit flexibility once a phase is complete, making late requirement changes costly.

CAgileCorrect

Agile divides work into short iterative sprints, providing frequent deliverables and review checkpoints that keep the customer actively involved throughout the engagement. It explicitly supports changing or reprioritizing requirements between sprints, which directly satisfies the customer's stated need for flexibility. No other listed methodology combines frequent updates with formal mechanisms for mid-project requirement changes.

DWaterfall

Waterfall locks requirements at the project start and executes phases linearly, making it unsuitable when the customer needs to change requirements as the project progresses.

Concept tested: Agile methodology for flexible iterative project delivery

Source: https://www.pmi.org/learning/library/agile-project-management-7764