According to ITIL®v3 framework, which risk management step analyzes threats and weaknesses that are introduced as a result of a service change?

The correct answer is C. risk assessment. See the full explanation below for the reasoning.

Question

According to ITIL®v3 framework, which risk management step analyzes threats and weaknesses that are introduced as a result of a service change?

Options

  • Arisk impact
  • Brisk mitigation
  • Crisk assessment
  • Drisk profile

How the community answered

(19 responses)
  • A
    11% (2)
  • B
    11% (2)
  • C
    74% (14)
  • D
    5% (1)