Cisco
350-060 · Question #29
Which key implementation mechanisms are responsible for ensuring that managed changes within the Operational Support Plan do not adversely impact the managed services?
The correct answer is C. change assessment, change triggers, and measurement of successful change. See the full explanation below for the reasoning.
Question
Which key implementation mechanisms are responsible for ensuring that managed changes within the Operational Support Plan do not adversely impact the managed services?
Options
- Achange assessment, change notifications, and measurement of successful change
- Bchange notifications, change triggers, and measurement of successful change
- Cchange assessment, change triggers, and measurement of successful change
- Dchange assessment, change notifications, and change triggers
How the community answered
(20 responses)- A5% (1)
- B5% (1)
- C75% (15)
- D15% (3)
Community Discussion