3301 · Question #46

You are planning a migration of an existing Avaya IMI-S Contact Center RIs.7.0 installation to Avaya Aura Contact Center (AACC) RIs.6.x. The Installation consists of standalone Contact Center Mai…

The correct answer is D. Migrate the CCMA server, then the CCMS server, then the CCT server. See the full explanation below for the reasoning.

Question

You are planning a migration of an existing Avaya IMI-S Contact Center RIs.7.0 installation to Avaya Aura Contact Center (AACC) RIs.6.x. The Installation consists of standalone Contact Center Mai Server (CCMS), Contact Center Manager Administration (CCMA) and Communication Control Toolkit servers. You plan to migrate each server during a separate maintenance window. In which order must you perform the server migrations?

Options

  • AMigrate the CCT server, then the CCMS server, then the CCMA server.
  • BMigrate the CCMS server, then the CCT server, then the CCMA server.
  • CMigrate the CCMA server, then the CCT server, then the CCMS server.
  • DMigrate the CCMA server, then the CCMS server, then the CCT server.

How the community answered

(21 responses)
  • B
    5% (1)
  • C
    14% (3)
  • D
    81% (17)

Community Discussion

No community discussion yet for this question.