220-1202 · Question #142

A network technician notices that most of the company's network switches are now end-of-life and need to be upgraded. What should the technician do first?

The correct answer is C. Document the change. Before any change is implemented, it must be documented as part of change management procedures. This ensures transparency, review, and tracking.

Submitted by eva_at· Mar 30, 2026Operational Procedures

Question

A network technician notices that most of the company's network switches are now end-of-life and need to be upgraded. What should the technician do first?

Options

  • AImplement the change
  • BApprove the change
  • CDocument the change
  • DSchedule the change

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    14% (3)
  • C
    76% (16)
  • D
    5% (1)

Explanation

Before any change is implemented, it must be documented as part of change management procedures. This ensures transparency, review, and tracking.

Topics

#Change management process#IT documentation#IT operations#End-of-life hardware