nerdexam
Cisco

200-301 · Question #933

What determines the sequence in which materials are planned during the material requirements planning (MRP) run?

The correct answer is C. The low-level code of the materials. During the Material Requirements Planning (MRP) run, the low-level code of materials dictates the planning sequence to ensure that dependent requirements are processed correctly.

Submitted by deeparc· Mar 5, 2026Network Fundamentals

Question

What determines the sequence in which materials are planned during the material requirements planning (MRP) run?

Options

  • AThe control parameters of the MRP run
  • BThe creation date of the materials
  • CThe low-level code of the materials
  • DThe replenishment lead time of the materials

How the community answered

(23 responses)
  • A
    9% (2)
  • C
    87% (20)
  • D
    4% (1)

Why each option

During the Material Requirements Planning (MRP) run, the low-level code of materials dictates the planning sequence to ensure that dependent requirements are processed correctly.

AThe control parameters of the MRP run

Control parameters of the MRP run, such as planning horizon or lot sizing, influence *how* the planning is executed but do not determine the hierarchical sequence based on material dependencies.

BThe creation date of the materials

The creation date of materials is an administrative detail and has no bearing on the logical sequence of planning material requirements based on their position in the product structure.

CThe low-level code of the materialsCorrect

The low-level code is a numeric identifier assigned to each material, indicating its lowest position in any product's bill of material (BOM). MRP planning processes materials starting from the highest low-level code (finished goods) down to the lowest (raw materials and components), ensuring that all components required for an assembly are planned only after the assembly itself has been addressed.

DThe replenishment lead time of the materials

The replenishment lead time is used to calculate when orders need to be placed to meet demand, but it does not determine the processing order of materials within the BOM hierarchy during the MRP run.

Concept tested: MRP planning sequence and low-level code

Source: https://www.netmba.com/operations/production/mrp

Topics

#low-level code#MRP run#material planning#production sequence

Community Discussion

No community discussion yet for this question.

Full 200-301 Practice