Select the three constraints that are missing in this Triple Constraint triangle.

The correct answer is B. Scope C. Cost F. Schedule. Scope, Time & Cost together are termed as the Triple Constraints of a Project. Risk avoidance involves changing the project plan to eliminate the risk or to protect the project objectives (time, cost, scope, quality) from its impact. The team might achieve this by changing…

Planning and Scheduling

Question

Select the three constraints that are missing in this Triple Constraint triangle.

Exhibit

1Z0-466 question #85 exhibit

Options

  • AUsability
  • BScope
  • CCost
  • DComplexity
  • EProduct
  • FSchedule

How the community answered

(38 responses)
  • A
    8% (3)
  • B
    74% (28)
  • D
    16% (6)
  • E
    3% (1)

Explanation

  • Scope, Time & Cost together are termed as the Triple Constraints of a Project. * Risk avoidance involves changing the project plan to eliminate the risk or to protect the project objectives (time, cost, scope, quality) from its impact. The team might achieve this by changing scope, adding time, or adding resources (thus relaxing the so-called "triple constraint") Note: Oracle 1Z0-466 Exam

Topics

#Triple Constraint#scope#cost#schedule