1Z0-466 · Question #54
Which statement is true about the Project Management Plan and the Project Workplan in OUM?
The correct answer is B. A change to one may necessitate a change to the other. OUM Manage provides the framework for consistently managing a project regardless of the project approach. The project manager must be familiar with the project approach being used, and must make the necessary adjustments in the Project Management Plan (as well as in the Project…
Planning and Scheduling
Question
Which statement is true about the Project Management Plan and the Project Workplan in OUM?
Options
- AThey are the same document.
- BA change to one may necessitate a change to the other.
- CThe Project Management Plan does not change after Project Startup, while the Project Workplan may
- DThe Project Workplan and Project Management plan have no Impact on one another.
How the community answered
(32 responses)- A9% (3)
- B84% (27)
- C3% (1)
- D3% (1)
Explanation
- OUM Manage provides the framework for consistently managing a project regardless of the project approach. The project manager must be familiar with the project approach being used, and must make the necessary adjustments in the Project Management Plan (as well as in the Project Workplan) to incorporate the concepts and activities that support the given approach. The same concepts apply to projects using offshore resources or third parties. * OUM Manage and Other Project Approaches OUM Manage can be used with any project approach. OUM Manage does not required any specific project approach. The project manager should adjust the Project Management Plan and Project Workplan in order to execute the project following the designated project approach.
Topics
#Project Management Plan#Project Workplan#document interdependency#change impact