Select four objectives of the OUM Manage Project Start UP phase.
The correct answer is B. Understand the client's objectives and expectations and validate project scope. C. Close out the contractual agreement. D. Baseline in Project Workplan, Finance Plan, and staffing needs. F. Agree with the client on project approach and document it in the Project Management Plan. The Project Start Up phase precedes the Inception phase. Project startup is where all of the project planning activities take place and where policies, procedures, and strategies are defined for each of the processes, which govern the conduct of the engagement.
Planning and Scheduling
Question
Select four objectives of the OUM Manage Project Start UP phase.
Options
- AManage the project resources to deliver on time and budget.
- BUnderstand the client's objectives and expectations and validate project scope.
- CClose out the contractual agreement.
- DBaseline in Project Workplan, Finance Plan, and staffing needs.
- EObtain a client reference.
- FAgree with the client on project approach and document it in the Project Management Plan.
- GEstablish the project infrastructure.
How the community answered
(64 responses)- A5% (3)
- B84% (54)
- E8% (5)
- G3% (2)
Explanation
- The Project Start Up phase precedes the Inception phase. Project startup is where all of the project planning activities take place and where policies, procedures, and strategies are defined for each of the processes, which govern the conduct of the engagement.
Topics
#Project Start UP phase#OUM Manage objectives#scope validation#project infrastructure