1Z0-466 · Question #3

What is not an activity in the OUM Manage Project Closure Phase?

The correct answer is B. Release Staff. The Project Closure phase occurs after the Production phase. During this phase, the project is "closed" (not A) from an administrative and contractual standpoint. This includes making sure that the project work (not E) products are complete and meet the customer's expectations…

Project Execution and Control

Question

What is not an activity in the OUM Manage Project Closure Phase?

Options

  • AContract Closure
  • BRelease Staff
  • CClose Scope Management
  • DClose User Acceptance Test
  • EClose Work Management

How the community answered

(29 responses)
  • A
    14% (4)
  • B
    76% (22)
  • C
    7% (2)
  • D
    3% (1)

Explanation

The Project Closure phase occurs after the Production phase. During this phase, the project is "closed" (not A) from an administrative and contractual standpoint. This includes making sure that the project work (not E) products are complete and meet the customer's expectations (not D); gaining final acceptance; and securing all documents for reuse, collection and retention.