What is not an approach for risk mitigation?

The correct answer is C. Accepting some of the risks and adding them to the Issues log since they will probably become an. See the full explanation below for the reasoning.

Question

What is not an approach for risk mitigation?

Options

  • AReducing the probability of occurrence by choosing an alternate approach
  • BReducing the impact of the risk by having a plan in place to immediately read to the event.
  • CAccepting some of the risks and adding them to the Issues log since they will probably become an
  • DAccepting some of the risks from the onset and controlling those risks throughout the project lifecycle.

How the community answered

(69 responses)
  • A
    9% (6)
  • B
    4% (3)
  • C
    71% (49)
  • D
    16% (11)