nerdexam
HRCI

SPHR · Question #14

Which of the following is the purpose of the business impact analysis when creating a business continuity plan?

The correct answer is A. To evaluate the potential effects of a disruption to an organization's critical business operations. A Business Impact Analysis (BIA) identifies how a disruption (e.g., cyberattack, disaster) would impact the organization's operations, revenue, and compliance, allowing for prioritization and recovery planning. Extract from HRCI-aligned HR knowledge (Risk Management)…

Risk Management

Question

Which of the following is the purpose of the business impact analysis when creating a business continuity plan?

Options

  • ATo evaluate the potential effects of a disruption to an organization's critical business operations
  • BTo identify time-sensitive or critical business functions, processes, and associated resources
  • CTo determine the impact of data loss or plan for data backup in the event of hardware failure
  • DTo establish a public relations communication plan in the event of an emergency

How the community answered

(20 responses)
  • A
    90% (18)
  • B
    5% (1)
  • D
    5% (1)

Explanation

A Business Impact Analysis (BIA) identifies how a disruption (e.g., cyberattack, disaster) would impact the organization's operations, revenue, and compliance, allowing for prioritization and recovery planning. Extract from HRCI-aligned HR knowledge (Risk Management): SPHR-level risk strategies include "conducting a BIA to understand the potential consequences of interruptions to business-critical functions." It's a foundational step in developing disaster recovery and continuity planning.

Topics

#business impact analysis#business continuity#risk assessment#disaster recovery

Community Discussion

No community discussion yet for this question.

Full SPHR Practice