What are two ways program risks can be categorized? (Choose two.)
The correct answer is D. Resolved E. Owned. See the full explanation below for the reasoning.
Question
What are two ways program risks can be categorized? (Choose two.)
Options
- AIdentified
- BExplained
- CDeferred
- DResolved
- EOwned
How the community answered
(47 responses)- A6% (3)
- B15% (7)
- C2% (1)
- D77% (36)