SAFE-RTE · Question #74

SAFE-RTE Question #74: Real Exam Question with Answer & Explanation

The correct answer is B. Product Management D. Release Train Engineer. See the full explanation below for the reasoning.

Question

Which two roles should facilitate an ART sync? (Choose two.)

Options

  • AEpic Owner
  • BProduct Management
  • CProduct Owner
  • DRelease Train Engineer
  • EScrum Master

Community Discussion

No community discussion yet for this question.