The Release Train Engineer ensures that Business Owners assign business value to what during Program Increment (PI) Planning?

The correct answer is D. Team-level PI Objectives. See the full explanation below for the reasoning.

Question

The Release Train Engineer ensures that Business Owners assign business value to what during Program Increment (PI) Planning?

Options

  • AProgram-level PI Objectives
  • BStories
  • CFeatures
  • DTeam-level PI Objectives

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    14% (3)
  • C
    5% (1)
  • D
    76% (16)