The Release Train Engineer ensures that Business Owners assign business value to what during Program Increment (PI) Planning?
The correct answer is D. Team-level PI Objectives. See the full explanation below for the reasoning.
Question
The Release Train Engineer ensures that Business Owners assign business value to what during Program Increment (PI) Planning?
Options
- AProgram-level PI Objectives
- BStories
- CFeatures
- DTeam-level PI Objectives
How the community answered
(21 responses)- A5% (1)
- B14% (3)
- C5% (1)
- D76% (16)