Product Management wants to prioritize a list of Features likely to be planned in the up-coming Program Increment (PI) meeting. What should Product Management use as the denominator of the weighted…

The correct answer is D. Job size based on relative estimation. See the full explanation below for the reasoning.

Question

Product Management wants to prioritize a list of Features likely to be planned in the up-coming Program Increment (PI) meeting. What should Product Management use as the denominator of the weighted shortest job first calculation?

Options

  • AThe T-shirt sizes for each of the Features
  • BThe actual business value of each Feature
  • CFeature size expressed in story points
  • DJob size based on relative estimation

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    12% (3)
  • C
    4% (1)
  • D
    81% (21)